I attended your training class a couple of months ago. We are continuing along with our scrum process, and we are learning a lot. I have one question - hope it is ok to ask. We did story point estimation as part of our team's Sprint planning, and came up with the total story points that we were going to tackle for the sprint. As we started working on some of the tasks, we realized that they were more difficult then we had originally estimated. Also, some people finished their tasks early and picked extra stuff from the backlog.
My question is as follows: Do you ever change the total story point value in the middle of the sprint (for either of the reasons that I mentioned above), and it if so, how would that work if your burn down is based on story points vs time. I know we talked about it in class, but I can't remember the answer.
I remember asking my own Scrum coach the same question a few years ago.